Søby

Energicenter Nord

2026

53.6 MWp

Søby Energipark is a 53.4 MWp solar park comprising 86,640 panels, which reduces CO₂ emissions by approximately 4,600 tonnes annually.

Located between Søby and Albøge, the park integrates renewable energy production with careful consideration for nature and wildlife. It is being developed as a unified project by Energicenter Nord.

Panel type:

BiFacial double glass 620W

Amount of paneles:

86,760 pcs.

Inverter:

154 pcs. 300 kW Huawei inverters

Mounting system:

Field

Orientation

South

Pitch:

20°

Total power:

53.4 MWp

Simulated produktion:

59.4 GWh/år

Migra Teknik offers to perform a range of tasks for the Søby Energipark project, focusing on grid connection clarifications, hardware installations, setups, testing, programming, and compliance with regulations. These include initial definitions, equipment wiring and configuration, various tests with the grid company, and fine-tuning of the PV plant:

  • Grid company connection clarification

  • Router (Grid company) type clarification (RJ45 or fiber)

  • RTU and communication protocol clarification (IEC 61850 or 104)

  • Definition of POC, PCOM, and PCI with grid company

  • Manual installation, wiring, and setup of remote acces OT, Smart Logger, and Park Controller (PPC)

  • Wiring of grid company router/RTU

  • Communication/ping test to grid company

  • FusionSolar setup

  • Inverter scan and setup

  • Temporarily limited ION test with grid company

  • Signal tests with grid company (Cold test)

  • Full ION test with grid company

  • Regulation tests with grid company (Hot tests)

  • SCADA programming and setup for third party (Balance Responsible)

  • FON test planning and cooperation, in accordance with RfG

  • FON re-test if needed after grid company report inspection

  • Ongoing programming, testing, correction, and fine-tuning of the PV plant

More projects with

Energicenter Nord

Energicenter Nord

Mesballe

2025

14.07 MWp